ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
1 | AMINET Phase I Proof of Concept | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 61% |
2 | | | | | | |
3 | General Project TO-Dos | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 82% |
4 | | | | | | |
5 | Define equipment required for project | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
6 | Procure equipment | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
7 | Create testing matrix for applications | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
8 | Setup G cards on all laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
9 | Create testing software testing suite for laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
10 | Install all testing software on laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
11 | Install testing software on PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
12 | Setup PCPhoneline adapters | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
13 | Setup PCPhoneline FXS/FXO on Cisco router and test | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
14 | Setup Cisco FXO card and test | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
15 | Order Maxrad sector antenna | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
16 | Order omni directional antenna | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
17 | Inventory project equipment and collect mac address for mgmt. Apps | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
18 | Order lighting blockers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
19 | Setup Proxim AP 2500 remember to set all cards to B standard | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
20 | Order cables | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
21 | Setup Cisco router and switch DS first three diagrams | 91 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
22 | Create Roaming test criteria | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
23 | Setup application servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
24 | Setup Cisco works and SNMP management of all devices | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 37% |
25 | Setup up wireless sniffer for B use only | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
26 | Setup up wireless sniffer for G use (layer 3 and up only) | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
27 | Setup spectrum analyzer | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
28 | Create portable outdoors kit for testing – battery and mobile AP kit | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 15% |
29 | Create testing criteria checklist sheets or forms on all laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
30 | Setup Neutrino for IDS testing and analysis | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
31 | Setup Cisco secure for security testing and authentication | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
32 | Get Cisco call manager or express if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 24% |
33 | Create a WS IP address to phone numbering repository | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
34 | Obtain headsets for laptops and PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
35 | Start QoS reading for 3550 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
36 | Start ospf mpls and bgp review for larger infrastructure | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
37 | Look into dual radio ap bridge. AP2500 first but something CPE | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
38 | Ethernet to RF converter???? | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
39 | Test MPLS IOS version on lab floater router | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 37% |
40 | Design cells and engineer RF circuits and diagram in Visio | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
41 | Order portable mast system if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
42 | Build portable mast system if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
43 | IP addressing plan for wireless cell and DS backend | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
44 | Setup local lab SIP open source SER on Linux serve if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
45 | Setup Skype and FWD accounts for all test clients | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
46 | Upgrade Proxim AP-2500 if appicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
47 | | | | | | |
48 | Phase I test site selection | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 69% |
49 | | | | | | |
50 | Locate optimal sites from lab for second antenna | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 36% |
51 | Locate range from lab site for client and roaming tests | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
52 | Look for location for temporary antenna mast and auto | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
53 | Sweep candidate site with netstumbler to obtain channels in use | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
54 | Map out with MS Mappoint if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
55 | | | | | | |
56 | Conduct Site survey of Phase I test site selections | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
57 | | | | | | |
58 | Complete all CWNP Site Survey forms | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
59 | Compile necessary surveying tools | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
60 | Draft RF coverage area diagrams for use during site survey AP/client placement | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
61 | Conduct visual site survey | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
62 | Conduct RF site survey | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
63 | | | | | | |
64 | RF Engineering Tasks | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
65 | | | | | | |
66 | Create RF circuit link budgets | 91 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
67 | Calculate Fresnel Zone and LOS based on Site Survey results | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
68 | K-Factor calculations | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
69 | Outline Attenuation/reflection/refraction and multipath points | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
70 | Diffraction analysis for Homes and business building in testing sites | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
71 | Attenuation analysis of trees for residential testing site (skewed winter- no leaves) | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
72 | Precipitation analysis for rain and snow | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
73 | Receiver RSSI calculations and tuning | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
74 | EIRP calculations and optimal power for req. for distance/speed/SOM | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
75 | Define tests for Fade Margin and SOM | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
76 | Antenna beam width calculations use YDI/AARL and Andrews software tools | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
77 | Determine proper antenna heights based on earlier Fresnel Zone analysis | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
78 | Noise analysis and triangulation see list on pg. 251 of Deploying License Free.. | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
79 | Include all antenna, power and RF info. on all architecture diagrams | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
80 | Feed system analysis design and documentation | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
81 | Distance doubling analysis based on Fade Margin/SOM | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
82 | | | | | | |
83 | Build out Phases | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 15% |
84 | | | | | | |
85 | Build out Phase I Single Omni Cell - Visio#1 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
86 | Build out Phase I Sector Cell - Visio #2 | 67 days | Mon 1/5/04 | Fri 4/2/04 | | 0% |
87 | Build out Phase I Dual PtMP Cells - Visio#3 and 3-a | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
88 | Build out Phase I Dual Cell/Dual Switch DS backbone - Visio #4 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
89 | Build out Phase I WISP backbone backend - Visio#5 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
90 | Build out Phase I WISP backbone backend - Viso#6 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
91 | Build out Phase I WISP backbone backend - Visio#7 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
92 | | | | | | |
93 | Testing Phases | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 15% |
94 | Cycle through each phase iteration with network architecture listed above | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
95 | use WISP testing matrix for each iteration | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
96 | | | | | | |
97 | Laptop to Laptop in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
98 | Laptop to PDA in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
99 | Laptop to Home in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
100 | Laptop to Lab internal Servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
101 | Laptop to Internet | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
102 | Laptop to Cisco FXS based phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
103 | Laptop to POTS phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
104 | POTS phone return call to Laptop | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
105 | All above tests with roaming | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 7% |
106 | All above tests with separate Voice/Data Cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 7% |
107 | | | | | | |
108 | PDA to Laptop in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
109 | PDA to PDA in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
110 | PDA to Home in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
111 | PDA to Lab internal Servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
112 | PDA to Internet | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
113 | PDA to Cisco FXS based phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
114 | PDA to POTS phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
115 | POTS phone return call to PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
116 | All above tests with roaming | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
117 | All above tests with separate Voice/Data Cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
118 | | | | | | |
119 | Home to Laptop in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
120 | Home to PDA in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
121 | Home to Lab internal Servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
122 | Home to Internet | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
123 | Home to Cisco FXS based phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
124 | Home to POTS phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
125 | Home phone return call to PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
126 | All above tests with roaming | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
127 | All above tests with separate Voice/Data Cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
128 | | | | | | |
129 | Document all testing results and publish on lab site | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
130 | | | | | | |