| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | AMINET Phase I Proof of Concept | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 61% |
| 2 | | | | | | |
| 3 | General Project TO-Dos | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 82% |
| 4 | | | | | | |
| 5 | Define equipment required for project | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 6 | Procure equipment | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 7 | Create testing matrix for applications | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 8 | Setup G cards on all laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 9 | Create testing software testing suite for laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 10 | Install all testing software on laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 11 | Install testing software on PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 12 | Setup PCPhoneline adapters | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 13 | Setup PCPhoneline FXS/FXO on Cisco router and test | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 14 | Setup Cisco FXO card and test | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 15 | Order Maxrad sector antenna | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 16 | Order omni directional antenna | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 17 | Inventory project equipment and collect mac address for mgmt. Apps | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 18 | Order lighting blockers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 19 | Setup Proxim AP 2500 remember to set all cards to B standard | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 20 | Order cables | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 21 | Setup Cisco router and switch DS first three diagrams | 91 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 22 | Create Roaming test criteria | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 23 | Setup application servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 24 | Setup Cisco works and SNMP management of all devices | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 37% |
| 25 | Setup up wireless sniffer for B use only | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 26 | Setup up wireless sniffer for G use (layer 3 and up only) | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 27 | Setup spectrum analyzer | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 28 | Create portable outdoors kit for testing – battery and mobile AP kit | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 15% |
| 29 | Create testing criteria checklist sheets or forms on all laptops | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 30 | Setup Neutrino for IDS testing and analysis | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 31 | Setup Cisco secure for security testing and authentication | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
| 32 | Get Cisco call manager or express if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 24% |
| 33 | Create a WS IP address to phone numbering repository | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 34 | Obtain headsets for laptops and PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 35 | Start QoS reading for 3550 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 36 | Start ospf mpls and bgp review for larger infrastructure | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 37 | Look into dual radio ap bridge. AP2500 first but something CPE | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
| 38 | Ethernet to RF converter???? | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 39 | Test MPLS IOS version on lab floater router | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 37% |
| 40 | Design cells and engineer RF circuits and diagram in Visio | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 41 | Order portable mast system if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 42 | Build portable mast system if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 43 | IP addressing plan for wireless cell and DS backend | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 44 | Setup local lab SIP open source SER on Linux serve if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
| 45 | Setup Skype and FWD accounts for all test clients | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 46 | Upgrade Proxim AP-2500 if appicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 47 | | | | | | |
| 48 | Phase I test site selection | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 69% |
| 49 | | | | | | |
| 50 | Locate optimal sites from lab for second antenna | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 36% |
| 51 | Locate range from lab site for client and roaming tests | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 52 | Look for location for temporary antenna mast and auto | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 10% |
| 53 | Sweep candidate site with netstumbler to obtain channels in use | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 54 | Map out with MS Mappoint if applicable | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 55 | | | | | | |
| 56 | Conduct Site survey of Phase I test site selections | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 57 | | | | | | |
| 58 | Complete all CWNP Site Survey forms | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 59 | Compile necessary surveying tools | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 60 | Draft RF coverage area diagrams for use during site survey AP/client placement | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 61 | Conduct visual site survey | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 62 | Conduct RF site survey | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 63 | | | | | | |
| 64 | RF Engineering Tasks | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 65 | | | | | | |
| 66 | Create RF circuit link budgets | 91 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 67 | Calculate Fresnel Zone and LOS based on Site Survey results | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 68 | K-Factor calculations | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 69 | Outline Attenuation/reflection/refraction and multipath points | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 70 | Diffraction analysis for Homes and business building in testing sites | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 71 | Attenuation analysis of trees for residential testing site (skewed winter- no leaves) | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 72 | Precipitation analysis for rain and snow | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 73 | Receiver RSSI calculations and tuning | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 74 | EIRP calculations and optimal power for req. for distance/speed/SOM | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 75 | Define tests for Fade Margin and SOM | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 76 | Antenna beam width calculations use YDI/AARL and Andrews software tools | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 77 | Determine proper antenna heights based on earlier Fresnel Zone analysis | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 78 | Noise analysis and triangulation see list on pg. 251 of Deploying License Free.. | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 79 | Include all antenna, power and RF info. on all architecture diagrams | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 80 | Feed system analysis design and documentation | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 81 | Distance doubling analysis based on Fade Margin/SOM | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 82 | | | | | | |
| 83 | Build out Phases | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 15% |
| 84 | | | | | | |
| 85 | Build out Phase I Single Omni Cell - Visio#1 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 100% |
| 86 | Build out Phase I Sector Cell - Visio #2 | 67 days | Mon 1/5/04 | Fri 4/2/04 | | 0% |
| 87 | Build out Phase I Dual PtMP Cells - Visio#3 and 3-a | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 88 | Build out Phase I Dual Cell/Dual Switch DS backbone - Visio #4 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 89 | Build out Phase I WISP backbone backend - Visio#5 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 90 | Build out Phase I WISP backbone backend - Viso#6 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 91 | Build out Phase I WISP backbone backend - Visio#7 | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 92 | | | | | | |
| 93 | Testing Phases | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 15% |
| 94 | Cycle through each phase iteration with network architecture listed above | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 95 | use WISP testing matrix for each iteration | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 96 | | | | | | |
| 97 | Laptop to Laptop in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 98 | Laptop to PDA in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 99 | Laptop to Home in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 100 | Laptop to Lab internal Servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 101 | Laptop to Internet | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 102 | Laptop to Cisco FXS based phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 103 | Laptop to POTS phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 104 | POTS phone return call to Laptop | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 105 | All above tests with roaming | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 7% |
| 106 | All above tests with separate Voice/Data Cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 7% |
| 107 | | | | | | |
| 108 | PDA to Laptop in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 109 | PDA to PDA in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 110 | PDA to Home in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 111 | PDA to Lab internal Servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 112 | PDA to Internet | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 113 | PDA to Cisco FXS based phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 114 | PDA to POTS phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 115 | POTS phone return call to PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 44% |
| 116 | All above tests with roaming | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 117 | All above tests with separate Voice/Data Cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 118 | | | | | | |
| 119 | Home to Laptop in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 120 | Home to PDA in cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 121 | Home to Lab internal Servers | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 122 | Home to Internet | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 123 | Home to Cisco FXS based phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 124 | Home to POTS phone | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 125 | Home phone return call to PDA | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 126 | All above tests with roaming | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 127 | All above tests with separate Voice/Data Cell | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 128 | | | | | | |
| 129 | Document all testing results and publish on lab site | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |
| 130 | | | | | | |
| 131 | Conduct Area Netstumbler sweep to see if existing WISP are in place | 92 days | Mon 12/1/03 | Fri 4/2/04 | | 0% |